If you haven’t started and don’t know where to, it’s highly recommended that you meet with Bruce to find out what you need to do and the pitfalls you are likely to come up against. At Teede Building Group we will spend some time working with you to find  out what it is you want to achieve and will show you how to get there.


A typical building process is highlighted below:

1 2 3 4

Client Design Process

  • Choose architect, draftsman
  • Project brief
  • Design drawings
  • Specifications

Builder Pricing
 

  • Submission and review of pricing and clarifications
  • Awarding of building contract

Construction Phase

  • Obtain building permit
  • Ongoing liaison with client and designers
  • Construction
  • Ongoing client site visits
  • Various independent compliance inspections - Building Ethics Australia (BEA)

Handover
 

  • Complete construction
  • Building certificates issues
  • Contract finalised
  • Independent compliance inspection and final sign off (BEA) and appointed building surveyor
  • Move in
  • Maintenance period